Plan Submittal Requirements and Inspections

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Plan Submittal and Review

Click here for Electronic Plan Submittal and Digital Signature Policy

Plans are reviewed on a first come first serve basis. Plan review times may take between 2-3 weeks for per submittal, depending on the size and complexity of the project, and may go through 2-3 plan reviews before final approval.


Resubmittals

Resubmittals must be uploaded to your permit through your eTRAKiT account. Log into your eTRAKiT account using your login credentials. Be sure to log in as “contractor” (use the contractor’s state license number or assigned AEC number for “username”) and enter your password. Under your active permits, locate the correct permit number and click on the paper clip icon to add your attachments.

Upload your resubmittal documents using the naming conventions below. 

2nd SUBMITTAL “PERMIT NO” PRECISE GRADING

2nd SUBMITTAL “PERMIT NO” HYDROLOGY STUDY

For third submittal;

3rd SUBMITTAL “PERMIT NO”PRECISE GRADING

3rd SUBMITTAL “PERMIT NO” HYDROLOGY STUDY 

Number of submittal should be updated for additional reviews (e.g. 4th, 5th) 

Responses for resubmittals are required to be provided in the format identified in the cover letter.  

Please allow 1-3 business days to process and route your resubmittal documents for review.


Inspections 

Engineering inspections for grading, street improvements, or storm drain improvements can be scheduled by emailing the Public Works team at pcinspections@palmdesert.gov. Requests must be submitted by 3:00 p.m. the day before the inspection is needed.


Top of Form Certification

Prior to the footing inspection with the Building Department, the Civil Engineer of Record for the project must submit a signed and stamped Top of Form Certification to the Public Works Department for review and approval. Click here to submit your Top of Form Certification. Please allow up to 3 business days for review and approval.


Plan Revisions

Substantial revisions to the approved plans require the submission of updated plans reflecting changes for review and approval. Updated plans should be submitted through eTRAKiT to start review process. Additional fees will apply.


Letter of Certification and Final Inspection

Before a final inspection can be scheduled, the engineer must submit a Letter of Certification for review and approval. Please click here to submit your request. Please allow up to 3 business days for review and approval of Letters of Certification.

Final inspection can be scheduled by emailing the Public Works team at pcinspections@palmdesert.gov.